Work near trees
Clearing and grubbing
GUIDE NOTE: Include the following paragraph
GUIDE NOTE: Include this clause when applicable.
Requirement
Clear the area indicated for the location of the sub-station easement in accordance with SG / SITE CLEARING, providing a satisfactory excavatable site, free of all services and obstructions which could interfere with the installation of an earthing electrode which may extend to a depth of 10m or more.
Levelling
Level the site by removal of topsoil and/or filling and suitable compaction. Any filling material shall be clean, stable and reasonably fine. Where the site is cut into a slope, provide retention of the bank and the diversion of all surface water from the sub-station.